The Massachusetts Department of Transportation has announced its schedule for replacing the Sagamore Bridge, part of $4.5 billion in Cape Cod bridge projects.
The notice for construction to proceed on the 1,400-foot-long Sagamore Bridge will be issued around Winter 2027, and the southbound bridge span is scheduled to float in around Fall 2031, according to MassDOT. The current bridge will be demolished in Winter 2033. All work on the estimated $2.1 billion project is expected to finish by Spring 2037.
The Sagamore Bridge and its southern counterpart, the 2,400-foot-long Bourne Bridge, are the main access between th